Leap Testing Leaps Ahead
Testing of the Leap-1 powerplant will involve 60 engine builds over the next three years. Engine certification is slated for 2015 ahead of commercial service entry on the Airbus A320neo in 2016, according to CFM International.
Testing of the Leap-1 powerplant will involve 60 engine builds over the next three years. Engine certification is slated for 2015 ahead of commercial service entry on the Airbus A320neo in 2016, according to CFM International.

With initial running of the new Leap-1 engine on schedule in September, CFM International (CFMI) has embarked on an “unprecedented” level of testing that should involve 20 developmental units by the end of next year and seven of the remaining eight planned examples before 2016 (when a final powerplant will take part in a short exercise–possibly a Leap-1C blade-out check).