Gary-Chicago Airport Delays Runway Expansion

Plans to expand the main runway at Chicago’s third commercial airport have hit another delay. The latest estimate now places completion in September next year.

The $167 million plan to lengthen Runway 12/30 and adjacent taxiway to 8,900 feet from 7,000 feet at Gary-Chicago International Airport (KGYY) in Gary, Ind., is stumbling in the wake of more extensive environmental remediation than initially anticipated; intransigence from railroads whose tracks must be relocated; the exodus last month of the airport’s lone airline, Allegiant; the possible exit of the airport’s most prestigious corporate tenant, Boeing; and the failure of the airport to attract up to $100 million more in private-sector financing for ancillary facilities.