The Sikorsky S-76D received its FAA type certificate in October, capping a development program that took seven years instead of the expected three years.
The Sikorsky S-76D received its FAA type certificate in October, capping a development program that took seven years instead of the expected three years.

The Sikorsky S-76D medium-twin helicopter achieved FAA type certification on October 12. Deliveries are now planned to begin later this quarter, as the backlog is “approaching half a billion dollars.” The manufacturer is now working on EASA certification.